Processing math: 100%

Learn and practice Aptitude questions and answers with explanation for interview, competitive exam (Pariksha Corner )

Wednesday, January 29, 2020

30 men can do a piece of work in 16 days. How many men would be required to do the same work in 20 days ?

30 men can do a piece of work in 16 days. How many men would be required to do the same work in 20 days ?
A12
B36
C48
D24

Answer is : 24

Explanation:

Days      Men

16          30

20           x

  20 : 16 = 30 : x

20×x=16×30

x=30×1620=24 men 

Akilesh Kharvi
answered May 29 '2017 at 10:45

All Comments

Post your answers here:

Post

Related Posts:

Categories