30 men can do a piece of work in 16 days. How many men would be required to do the same work in 20 days ?

30 men can do a piece of work in 16 days. How many men would be required to do the same work in 20 days ?
A12
B36
C48
D24

Answer is : 24

Explanation:

Days      Men

16          30

20           x

\(\therefore\)  20 : 16 = 30 : x

\(\therefore  20 \times x = 16 \times 30\)

\(x = \frac{30\times16}{20} = 24\text{ men }\)

Akilesh Kharvi
answered May 29 '2017 at 10:45