Smita can finish a work in 12 days and Shyam can finish the same work in 9 days. After working together for 4 days they both leave the job. What is the fraction of unfinished work?

Smita can finish a work in 12 days and Shyam can finish the same work in 9 days. After working together for 4 days they both leave the job. What is the fraction of unfinished work?
Aa) 1/7
Bb) 5/9
Cc) 2/9
Dd) 3/ 4

Correct answer is: 2/9

Explanation:

Smita can finish a work in 12 days

Per day work of Smita = 1/12

Shyam can finish the same work in 9 days

Per day work of Shyam = 1/9

Per day work done if both work together = 1/12 + 1/9

=3+436

=736

If they work for 4 days =4×736

=79

Remaining unfinished work =179

=29