If A, B, and C can do a piece of work in 15, 30, and 60 days respectively. In how many days together they will do the same work?

If A, B, and C can do a piece of work in 15, 30, and 60 days respectively. In how many days together they will do the same work?
A10 days
B12 days
C60/11 days
D60/7 days

correct answer is: option d) [60/7 days]
Explanation: Let A, B, and C complete the work in 15, 30, and 60 days respectively.
Work done by A in 1 day = 115
Work done by B in 1 day = 130
Work done by C in 1 day = 160
Work done by A, B, and C together in 1 day = 115+130+160 = 4+2+160 = 760
Therefore, the number of days required for A, B, and C to complete the work together = 607 days.

  • Option a: 10 days is incorrect because the combined work rate is faster than this.
  • Option b: 12 days is incorrect because the combined work rate is faster than this.
  • Option c: 60/11 days is incorrect because the sum of the individual work rates is not 11/60.