Learn and practice Aptitude questions and answers with explanation for interview, competitive exam (Pariksha Corner )

Monday, April 7, 2025

If Jaya and Shushma together can complete a given task together in 40 days, if Jaya left the job after working for 15 days, and the remaining job was done by Shushma in 40 days, then in how many days Shushma can complete the whole work alone?

If Jaya and Shushma together can complete a given task together in 40 days, if Jaya left the job after working for 15 days, and the remaining job was done by Shushma in 40 days, then in how many days Shushma can complete the whole work alone?
A64 days
B72 days
C80 days
D56 days

correct answer is: 64 days
Explanation: Let's denote the total work as 1 unit.

Jaya and Shushma together can complete the work in 40 days,

so their combined work rate is 140 per day.

Jaya works for the first 15 days, completing 15×140=1540=38 of the work.

The remaining work is 138=58

Shushma completes this remaining work in 40 days,

so her work rate is 58÷40=5320=164 per day.

Therefore, Shushma can complete the whole work alone in 64 days

Akhilesh
answered Apr 9 '25 at 06:52

Post your answers here:

Post

Related Posts:

Categories