A work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days P alone can finish the work ?

A work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days P alone can finish the work ?
A10
B20
C30
D60
View Answer

30 men can do a piece of work in 16 days. How many men would be required to do the same work in 20 days ?

30 men can do a piece of work in 16 days. How many men would be required to do the same work in 20 days ?
A12
B36
C48
D24
View Answer

M and N can do a work in 10 days and 15 days respectively. If M starts on the work and both work alternately day after day, in how many days will the work be completed ?

M and N can do a work in 10 days and 15 days respectively. If M starts on the work and both work alternately day after day, in how many days will the work be completed ?
A10
B12
C8
D9
View Answer

A is twice as good a workman as B and together they finish a piece of work in 14 days. The number of days taken by A alone to finish the work is :

A is twice as good a workman as B and together they finish a piece of work in 14 days. The number of days taken by A alone to finish the work is :
A11
B21
C28
D42
View Answer

A certain number of persons can complete a work in 100 days. If there be 10 persons less, it would have taken 10 days more for the work to be completed. The number of persons in the beginning was

A certain number of persons can complete a work in 100 days. If there be 10 persons less, it would have taken 10 days more for the work to be completed. The number of persons in the beginning was
A90
B105
C110
D120
View Answer