A work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days P alone can finish the work ?

A work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days P alone can finish the work ?
A10
B20
C30
D60

Correct anwer is:30

Explanation: