‘x’ number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is

‘x’ number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
A6
B10
C12
D15

Correct answer is: 12

Explanation:

rahul
answered Feb 2 '2020 at 8:44