Two men alone or three women alone can complete a piece of work in 4 days. In how many days can 1 woman and one man together complete the same piece of work ?

Two men alone or three women alone can complete a piece of work in 4 days. In how many days can 1 woman and one man together complete the same piece of work ?
A6 days
B $$\frac{24}{5} \text { days}$$
C$$\frac{12}{1.75}\text{ days}$$
DCannot be determined
View Answer

4 girls can do a piece of work in 8 days, 3 boys can do the same piece of work in 9 days, 7 men do the same piece of work in 2 days and 5 women can do the same piece of work in 4 days. Who is least efficient ?

4 girls can do a piece of work in 8 days, 3 boys can do the same piece of work in 9 days, 7 men do the same piece of work in 2 days and 5 women can do the same piece of work in 4 days. Who is least efficient ?
ABoys
BGirls
CWomen
DMen
View Answer

Thursday, January 30, 2020

A water tank has three taps A, B and C.Tap A, when opened, can fill the water tank alone in 4 hours. Tap B, when opened, can fill the water tank alone in 6 hours and tap C, when opened, can empty the water tank alone in 3 hours. If taps A, B and C are opened simultaneously how long will it take to fill the tank completely ?

A water tank has three taps A, B and C.Tap A, when opened, can fill the water tank alone in 4 hours. Tap B, when opened, can fill the water tank alone in 6 hours and tap C, when opened, can empty the water tank alone in 3 hours. If taps A, B and C are opened simultaneously how long will it take to fill the tank completely ?
A10 hours
B17 hours
C18 hours
D12 hours
View Answer

Vikas gets Rs 350 for every day that he works. If he earns Rs 9,800 in a month of 31 days, for how many days did he work ?

Vikas gets Rs 350 for every day that he works. If he earns Rs 9,800 in a month of 31 days, for how many days did he work ?
A25 days
B30 days
C24 days
D28 days
View Answer

2 men can complete a piece of work in 6 days. 2 women can complete the same piece of work in 9 days, where as 3 children can complete the same piece of work in 8 days. 3 women and 4 children worked together for 1 day. If only men were to finish the remaining work in 1 day, how many total men would be required ?

2 men can complete a piece of work in 6 days. 2 women can complete the same piece of work in 9 days, where as 3 children can complete the same piece of work in 8 days. 3 women and 4 children worked together for 1 day. If only men were to finish the remaining work in 1 day, how many total men would be required ?
A 4
B8
C6
DCannot be determined
View Answer

8 men can complete a piece of work in 20 days. 8 women can complete the same workin 32 days. In how many days will 5 men and 8 women together complete the samework ?

8 men can complete a piece of work in 20 days. 8 women can complete the same workin 32 days. In how many days will 5 men and 8 women together complete the samework ?
A16 days
B12 days
C14 days
D10 days
View Answer

3 men can complete a piece of work in 6 days. 5 women can complete the same work in 18 days. In how many days will 4 men and 10 women together complete the same work ?

3 men can complete a piece of work in 6 days. 5 women can complete the same work in 18 days. In how many days will 4 men and 10 women together complete the same work ?
A 3 days
B5 days
C2 days
D4 days
View Answer