8 men can finish a piece of work in 40 days. If 2 more men join with them, then the work will be completed in
8 men can finish a piece of work in 40 days. If 2 more men join with them, then the work will be completed in
8 men can finish a piece of work in 40 days. If 2 more men join with them, then the work will be completed in
A man, a woman and a boy together complete a piece of work in 3 days. If a man alone can do it in 6 days and a boy alone in 18 days, how long will a woman take to complete the work ?
‘x’ number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
A work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days P alone can finish the work ?
30 men can do a piece of work in 16 days. How many men would be required to do the same work in 20 days ?
M and N can do a work in 10 days and 15 days respectively. If M starts on the work and both work alternately day after day, in how many days will the work be completed ?
A is twice as good a workman as B and together they finish a piece of work in 14 days. The number of days taken by A alone to finish the work is :