8 men and 4 women together can complete a piece of work in 6 days. Work done by a man in one day is double the work done bya woman in one day. If 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined, in how many more days will the work be completed ?
8 men and 4 women together can complete a piece of work in 6 days. Work done by a man in one day is double the work done bya woman in one day. If 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined, in how many more days will the work be completed ?
A5 days
B 8 days
C6 days
D4 days